ReviewBuilding
Review Date03/16/2021
StatusRejected
Comments
Door schedule and hardware information is not found on the drawings. Please provide the schedule and door hardware schedule on the drawings to verify compliance with the door and hardware requirements of the Virginia Construction Code.
Code Reference: VCC 2015 Sec 1010
  



  
 